Columbus Family Practice and Tooley’s Pharmacy

Just completed in Columbus, NE.  Two building project included the family practice and the other Tooley’s Pharmacy.  A total of 225 squares of Canyon Shake (Timberwood) with the batten and counterbatten system.  Project took a total of 6 weeks with quite a few rain days.  This project was new construction so we have no before pictures, however here are a bunch of after picks.